Manufacturing Facility

Manufacturing Facility Construction Company
Work completed in a 3-day shutdown.  The Scope of Work included:
  • Remove and re-installed existing roofing system and associated structural steel
  • Removed and installed a new Heat Exchanger
  • Removed and installed new Steam Valves
  • Removed and installed Katheen tanks/motors
  • Removed existing K-7 Unit with associated duct work, lift fan units
  • Replaced K-7 Unit bases
  • Demolished 300-sf of corrugated decking
  • Removed and re-installed 1,000-sf of floor grating
  • Replaced damaged structural steel in the existing flooring system.