Lake Sequoya Raw Water Intake & Pump Station
Environmental

Lake Sequoya Raw Water Intake & Pump Station

LOCATION

Highlands, NC

PROJECT SIZE

Treatment Capacity: 2.0 MGD raw water intake and pump station

ENGINEER

McGill Associates

The project consisted of the construction of a new 2.0 MGD capacity raw water intake and pump station for the Town of Highlands on Lake Sequoya. Work included:

  • A raw water intake screen with air burst system
  • 140 ft of 14″ raw water intake piping laid in granite. Installation of this pipe required that the entire lake be drawn down using a by-pass pumping system and other dam modifications were made while the lake was down
  • A pre-cast concrete wet well that was approximately 33 ft deep. 20 ft of this was in solid granite
  • A 750 SF pump station building with valves, controls and miscellaneous piping. Installation of approximately 2,100 LF of 12″ diameter raw water transmission main. 90% of this line was laid down one lane of a major highway which had to be resurfaced upon completion
  • Resurfacing of approximately 1550 SF of the existing dam
  • Epoxy injection of minor cracks in the existing dam

Let’s Get Building

As Builders–Innovators–Partners, Langston Construction is ready to deliver what we promise: a safe, trouble-free project that satisfies your budget and timeline goals.

LANGSTON CONSTRUCTION COMPANY, LLC

PO BOX 560 | 125 LANGSTON ROAD

PIEDMONT, SC 29673-0560

© Langston Construction Co. of Piedmont, LLC